Location

Middle Paxton Township

Schedule

Winter 2024 -Fall 2025

Status/Phase

Design

Background:

CRW’s primary supply raw water transmission main is a 42‑inch reinforced concrete cylinder pipe constructed in the late 1930s. The original isolation and air release valves on the main require maintenance and repair.  

Project Purpose:

Replace broken isolation valves on the raw water transmission main to ensure operational reliability.  

Project Summary:

Replace a leaking 42‑inch isolation valve in Middle Paxton Township. The project will be financed from 2018 series bonds/cash.

Signup for our newsletter

"*" indicates required fields

Enter your email address to subscribe
This field is for validation purposes and should be left unchanged.