Final Street Restoration
Capital Region Water’s contractor will performing final street restoration at the seven excavation sites beginning April 17th. This street restoration will include the removal of all temporary asphalt and installation of permanent asphalt. Streets may be closed temporarily while this work takes place.
Street Restoration Location |
Estimated Timeline |
Parkway Driver between Briggs St and Poplar St | Complete |
Oxford Street between 7th St and Jefferson St | April 17 – April 21 |
North 4th Street between Maclay St and Geiger St | April 17 – April 21 |
Green Street between Boas St and Forster St | April 24 – April 28 |
Green Street between Clinton St and Harrisburg St | April 24 – April 28 |
Crescent Street between Mulberry St and Haehnlen St | April 24 – April 28 |
Bailey Street between 13th St and 12th St | May 1 – May 5 |
Project Overview
Capital Region Water kicked off a $1.3 million sewer replacement project on Monday, November 14th. This project will resolve broken sewer mains and will ensure reliable wastewater service for several decades by replacing and renewing aging sewer infrastructure at ten locations in Harrisburg, PA.
This project was initiated after structural deficiencies in the sewers were identified through video inspection of sewer pipes in 2015 and 2016.
The seven locations listed below will require street excavation to install new sewer mains:
Project Location |
Estimated Timeline |
Notes |
Green Street between Boas St and Forster St | November 14th – Mid-December | 277 feet of new sewer |
Green Street between Clinton St and Harrisburg St | November 14th – Mid-December | 247 feet of new sewer |
North 4th Street between Maclay St and Geiger St | Mid-December – End of December | Repairing 20 feet of sewer |
Oxford Street between 7th St and Jefferson St | Mid-December – Mid-January | 359 feet of new sewer |
Crescent Street between Mulberry St and Haehnlen St | Mid-December – End of December | 131 feet of new sewer |
Bailey Street between 13th St and 12th St | End of December– End of February | 868 feet of new sewer |
Parkway Driver between Briggs St and Poplar St | Mid December – End of December | 37 feet of new sewer |
Potential impacts of this construction include:
Street closures, no parking, construction noise, and temporary sewer service interruptions. Working hours will be 7:00 AM – 5:00PM, Monday through Friday. This project will not require access to customers’ homes. When the pipe replacement is complete, the road will be temporarily patched until final street restoration in the spring of 2017. Customers in the affected area will be notified door to door prior to construction with additional details.
Cured-in-place pipe:
Three sewer mains on Crescent Street, Maclay Street, and Parkway Drive will be renewed with a cured-in-placed pipe (inserting a new pipe into an existing pipe) and do not require street excavation. Potential impacts from the cured in place lining include: temporary traffic disturbance, temporary sewer service interruption. Customers in the affected area will be notified door to door prior to this work with additional details.
Questions:
Customers with questions can contact Capital Region Water by phone at 888-510-0606 or by email at info@capitalregionwater.com. Capital Region Water will also have a representative on site during working hours.