Construct green stormwater infrastructure (GSI) at 4th & Dauphin Park, including rain gardens, a pervious basketball court and tree pits.

Schedule

Construction Fall 2020 – Summer 2021

Status/Phase

Completed - Park Opened August 19th

Background:


CRW is partnering with the City and DCNR to renovate a City playground with the design to capture and manage stormwater from the surrounding area. This is the 5th and final park in a series collaboration between the parties.

Project Purpose:


Capture and manage stormwater in green stormwater elements.

Project Summary:


Construct green stormwater elements (rain gardens, pervious basketball court, and tree pits).

The project will be financed by a PENNVEST low-interest loan.