Repair segment of raw transmission water main.

Location

Along Mountain Line

Schedule

2021

Status/Phase

Completed

Background:

CRW’s primary supply raw water transmission main passes through wooded land crossed by numerous seasonal streams. The alignment should be accessible for access by CRW for routine maintenance or emergency repair. The alignment has become overgrown following a period without any clearing operations. Phase 1 was completed in 2018, clearing 8 miles of the alignment. Phase 2 planned for early 2021 will clear the remaining 10 miles of alignment to the Water Services Center


Project Purpose:

A clearing operation is required to restore operational access.

Project Summary:

Clear 20-ft wide swath along the 10-mile transmission main alignment between Dauphin Borough and Harrisburg City.


Project will be financed from 2018 series bonds/cash.